From Earthworks to Asphalt: Engineering Nasarawa's 75 km Road

Building 75 km of six-lane dual carriageway takes large-scale earthworks and a carefully layered pavement. The Schedule of Activities for ICCO's Nasarawa urban roads project shows how much work went into the road before the final asphalt was laid, from surveys and soil tests to more than a million cubic metres of embankment fill.


This article follows the road from the ground up: the design studies that shaped it, the earthworks that formed its platform, and the six pavement layers that now carry Nasarawa's traffic.

Key facts

  • Road length: 75 km of six-lane dual carriageway
  • Right-of-way cleared: 3,375,000 m²
  • Excavation: 525,000 m³ common + 15,000 m³ in rock
  • Embankment fill: 1,125,000 m³
  • Asphalt: 50 mm binder course + 50 mm wearing course
  • Certified complete: 27 June 2026

Design first: the studies behind the road

The project began with a complete design for the 75 km dual carriageway. ICCO carried out:

  • Topographic surveys, which map the shape and levels of the ground along the route;
  • Geotechnical investigations, which test the soils the road will sit on;
  • Traffic and axle-load studies, which measure how many vehicles use the route and how heavy they are;
  • Hydrological and hydraulic studies, which estimate how rainwater flows towards the road; and
  • detailed geometric, pavement, drainage, bridge, road-safety and lighting designs.

Traffic and axle-load studies matter because they show how many vehicles, and how heavy, the road must carry over its life. These figures set the thickness of each pavement layer. A road designed for light cars alone would fail quickly under loaded trucks, so getting the loading right at the start protects the whole investment.

Preparing the ground

On site, crews cleared and grubbed 3,375,000 m² of right-of-way, an area equivalent to a strip about 45 m wide along the full 75 km. Clearing and grubbing removes vegetation, stumps and roots so that the road is built on firm material rather than organic soil that would compress over time.

The crews then carried out 525,000 m³ of common excavation in cut and 15,000 m³ of excavation in rock. Total embankment fill, drawn from cut and borrow areas, reached 1,125,000 m³.

Earthworks activity Executed quantity
Clearing and grubbing of right-of-way 3,375,000 m²
Common excavation in cut 525,000 m³
Excavation in rock 15,000 m³
Embankment fill from cut and borrow areas 1,125,000 m³

Reusing excavated material as fill reduces the need to bring in material from elsewhere, which saves haulage and limits disturbance to surrounding land. The embankments give the road a stable, raised platform above the surrounding ground.

Building the pavement, layer by layer

The pavement was built in layers, each spreading the load before it reaches the soil below. A truck tyre presses on a small patch of asphalt; by the time that force has passed down through the base, subbase and capping, it is spread over a much wider area, so the natural ground underneath carries only a fraction of the original pressure.


Layer (bottom to top) Executed quantity What it does
Improved subgrade / capping 363,375 m³ Strengthens the formation and gives a uniform working platform
Granular subbase 454,500 m³ Spreads loads and supports the base course
Graded crushed stone base course 436,500 m³ Main load-carrying layer beneath the asphalt
Prime coat 2,182,500 m² Seals the base and helps the asphalt bond to it
Asphalt binder course, 50 mm 1,642,500 m² Adds strength to the bound layers
Asphalt wearing course, 50 mm 2,092,500 m² Gives drivers a smooth, durable riding surface

The prime coat seals the crushed stone base and helps the asphalt bond to it. The binder course adds strength, while the wearing course gives drivers a smooth, durable riding surface. Because the wearing course is the layer tyres actually touch, it is the one road users notice: its evenness decides how comfortable and quiet the journey feels.

Why the layers matter

Each layer is chosen for a job. Granular layers carry and spread load and let water drain away; the asphalt layers resist wear and keep water from soaking down into the base. When any layer is thinner or weaker than it should be, the road above it starts to rut and crack. That is why the pavement design depends on the traffic and soil data gathered at the start of the project.

Certified complete

All 75 km of road construction and dualisation works were completed and certified on 27 June 2026, as recorded in the Certificate of Completion issued by the Nasarawa State Urban Development Board.

More on the Nasarawa 75 km urban roads

This article is part of a five-part series on the project:

Frequently asked questions

How much earth was moved on the Nasarawa 75 km road?

Crews carried out 525,000 m³ of common excavation and 15,000 m³ of rock excavation, and placed 1,125,000 m³ of embankment fill drawn from cut and borrow areas.

What are the pavement layers of the Nasarawa road?

From the bottom up: improved subgrade or capping, granular subbase, graded crushed stone base course, prime coat, a 50 mm asphalt binder course and a 50 mm asphalt wearing course.

What does a prime coat do?

The prime coat seals the crushed stone base and helps the asphalt layers bond to it.

Why were traffic and axle-load studies needed?

They show how many vehicles, and how heavy, the road must carry over its life. These figures set the thickness of each pavement layer.